How to Prepare Rate Analysis for P.C.C. Work

Image
Q. Prepare Rate  analysis  for a PCC work (1:3:6). Sol n .:-              Given: -  Concrete grade = M10 (1:3:6)                                           Take = 10m 3  volume for PCC Add 52% extra for voids to get dry vol m . of Concrete. Volume of dry concrete = 1.52×10                                                    = 15.2 m 3 Quantity of cement = (15.2/(1+3+6)   ) ×1              ...

PREPARING RATE ANALYSIS



Sr. No.
Material
Unit
Quantity
Rate
Amount
1.





2.






Sr. No.
Labour
Men
Rate
Per(Day)
Amount
1.





2.






D. Total cost of Labour & Materials = B+C
Add 1.5% Water Charges = 1.5 % × (B+C)
Add 10% Contractor Charges = 10 % × (B+C)
          ­                                                ___________________________________
                      Grand Total =


Name of work
Quantity
Head
Mason
Mason
Male Mazdoor
Boy/ WomanCoolie
Bhisti
Scaf-folding
Sundries
T&P
Cement
Concrete
(PCC)
10 m3
     ½
12
18
3
-
Rs. 100
Brick work
10 m3
1
8
6
6
1
Rs. 250
Rs. 100
Plaster work
100 m2
10
15
2
1
Rs. 250
Rs. 100
RCC Work
10 m3
1
3
12
20
6
-
Rs. 100


1. Bending, cranking & binding for steel bars
Blacksmith
8 nos.
Rs. 350/-
Mazdoor
8 nos.
Rs. 250/-
T&P
-
Rs. 100 (lumpsum)

2. Centering & shuttering
Carpenter
10 nos.
Rs. 350/-
Mazdoor
10 nos.
Rs. 250/-
T&P
-
Rs. 100 (lumpsum)

1. Head Mason = Rs. 400/- per day
2. Mason = Rs. 350/- per day
3. Male Mazdoor = Rs. 200/- per day
4. Boy/ Woman Coolie = Rs. 150/- per day
5. Bhisti = Rs. 250/- per day

Cement = Rs. 350/- per bag
Sand = Rs. 1000/- per m3
Aggregate = Rs. 1200/- per m3
Brick (I-Class) = Rs. 4/- per brick
Steel = Rs. 50/- per kg.
Binding wire = Rs. 40/- per kg.

Scaffolding = Rs. 250/-
Sundries T&P = Rs. 100/-


To better understand watch out this video






Comments

Popular posts from this blog

How to Prepare Rate Analysis for R.C.C. Work

How to Prepare Rate Analysis for P.C.C. Work

LONG WALL & SHORT WALL METHOD