How to Prepare Rate Analysis for P.C.C. Work

Image
Q. Prepare Rate  analysis  for a PCC work (1:3:6). Sol n .:-              Given: -  Concrete grade = M10 (1:3:6)                                           Take = 10m 3  volume for PCC Add 52% extra for voids to get dry vol m . of Concrete. Volume of dry concrete = 1.52×10                                                    = 15.2 m 3 Quantity of cement = (15.2/(1+3+6)   ) ×1              ...

PREPARING RATE ANALYSIS



Sr. No.
Material
Unit
Quantity
Rate
Amount
1.





2.






Sr. No.
Labour
Men
Rate
Per(Day)
Amount
1.





2.






D. Total cost of Labour & Materials = B+C
Add 1.5% Water Charges = 1.5 % × (B+C)
Add 10% Contractor Charges = 10 % × (B+C)
          ­                                                ___________________________________
                      Grand Total =


Name of work
Quantity
Head
Mason
Mason
Male Mazdoor
Boy/ WomanCoolie
Bhisti
Scaf-folding
Sundries
T&P
Cement
Concrete
(PCC)
10 m3
     ½
12
18
3
-
Rs. 100
Brick work
10 m3
1
8
6
6
1
Rs. 250
Rs. 100
Plaster work
100 m2
10
15
2
1
Rs. 250
Rs. 100
RCC Work
10 m3
1
3
12
20
6
-
Rs. 100


1. Bending, cranking & binding for steel bars
Blacksmith
8 nos.
Rs. 350/-
Mazdoor
8 nos.
Rs. 250/-
T&P
-
Rs. 100 (lumpsum)

2. Centering & shuttering
Carpenter
10 nos.
Rs. 350/-
Mazdoor
10 nos.
Rs. 250/-
T&P
-
Rs. 100 (lumpsum)

1. Head Mason = Rs. 400/- per day
2. Mason = Rs. 350/- per day
3. Male Mazdoor = Rs. 200/- per day
4. Boy/ Woman Coolie = Rs. 150/- per day
5. Bhisti = Rs. 250/- per day

Cement = Rs. 350/- per bag
Sand = Rs. 1000/- per m3
Aggregate = Rs. 1200/- per m3
Brick (I-Class) = Rs. 4/- per brick
Steel = Rs. 50/- per kg.
Binding wire = Rs. 40/- per kg.

Scaffolding = Rs. 250/-
Sundries T&P = Rs. 100/-


To better understand watch out this video






Comments

Popular posts from this blog

How to Prepare Rate Analysis for P.C.C. Work

Different types of Plan in Civil engineering

How to Prepare Rate Analysis for R.C.C. Work