Q. Prepare Rate analysis for a PCC work (1:3:6). Sol n .:- Given: - Concrete grade = M10 (1:3:6) Take = 10m 3 volume for PCC Add 52% extra for voids to get dry vol m . of Concrete. Volume of dry concrete = 1.52×10 = 15.2 m 3 Quantity of cement = (15.2/(1+3+6) ) ×1 ...
Q. Prepare Rate analysis for a PCC work (1:3:6). Sol n .:- Given: - Concrete grade = M10 (1:3:6) Take = 10m 3 volume for PCC Add 52% extra for voids to get dry vol m . of Concrete. Volume of dry concrete = 1.52×10 = 15.2 m 3 Quantity of cement = (15.2/(1+3+6) ) ×1 ...
The different types of plan are explained below- (i) Site plan (ii) Layout plan (iii) Index plan (iv) Key plan (v) Services plan. 1. Site Plan - Site plan is a general layout of the site drawn as a line diagram to a small scale along with the surrounding plots of land & adjoining roads to place the site and to represented the means of access. The orientation of the building along with the North direction is represented in the site plan. In site plan the position of sewer lines & water etc., may also be provided. Site plans are drawn to a scale of 1 cm = 5 m to 1 cm = 10 m in the working drawings. 2. Layout Plan - For a project consisting of a number of various structures, a layout i.e. the comparative positions of all the various units to be constructed land is represented to a scale generally 1 cm = 10 m to 1 cm = 20 m and is called a layout plan. This helps to form a general idea and ...
Comments
Post a Comment