How to Prepare Rate Analysis for P.C.C. Work
Soln.:-
Given: - Concrete grade = M10 (1:3:6)
Take = 10m3 volume for PCC
Add 52% extra for voids to get dry volm. of Concrete.
Volume of dry concrete = 1.52×10
= 15.2 m3
Quantity of cement = (15.2/(1+3+6) ) ×1
= 1.52 m3
No. of bags = 1.52×28.5
= 43.32 bags ≅ 44 bags (say)
Quantity of sand = (1.52 ) ×3
= 4.56 m3
Quantity of aggregate = (1.52) ×6
= 9.12 m3
Sr. No.
|
Material
|
Unit
|
Quantity
|
Rate
|
Amount
| |
₹
|
P.
| |||||
1.
|
Cement
|
Bags
|
44
|
350/-
|
15400
|
00
|
2.
|
Sand
|
m3
|
4.56
|
1000/-
|
4560
|
00
|
3.
|
Aggregate
|
m3
|
9.12
|
1200/-
|
10944
|
00
|
Total Amount = ₹ 30904.00/-
|
Sr. No.
|
Labour
|
Men (nos.)
|
Rate
|
Per(Day)
|
Amount
| |
₹
|
P.
| |||||
1.
|
Head Mason
|
½
|
400/-
|
Day
|
200
|
00
|
2.
|
Mason
|
1½
|
350/-
|
Day
|
525
|
00
|
3.
|
Male Mazdoor
|
12
|
200/-
|
Day
|
2400
|
00
|
4.
|
Coolie
|
18
|
150/-
|
Day
|
2700
|
00
|
5.
|
Bhisti
|
3
|
250/-
|
Day
|
750
|
00
|
6.
|
T&P
|
Lump sum
|
100/-
|
__
|
100
|
00
|
Total Amount = ₹ 6675.00/-
|
Total cost = Cost of materials+ Cost of labours
= 30904.00+6675.00
Total cost = ₹ 37579.00/-
Add 1.5% Water Charges of total cost
= (1.5/100 ) ×37579
Water charges = ₹ 563.69/- (say = ₹ 564.00/-)
Add 10% Contractor’s Charges = (10/100 ) ×37579
Contractor’s Charges = ₹ 3758.90/- (say = ₹ 3759.00/-)
____________________________________________
Grand total = 37579.00+564.00+3759.00
= ₹ 41901.00/-