How to Prepare Rate Analysis for P.C.C. Work

Soln.:-
            Given: - Concrete grade = M10 (1:3:6)  
                                       Take = 10m3 volume for PCC
Add 52% extra for voids to get dry volm. of Concrete.
Volume of dry concrete = 1.52×10
                                                  = 15.2 m3
Quantity of cement = (15.2/(1+3+6) ) ×1
                                         = 1.52 m3
      No. of bags             = 1.52×28.5
                                         = 43.32 bags ≅ 44 bags (say)

Quantity of sand = (1.52 ) ×3
                                    = 4.56 m3

Quantity of aggregate = (1.52) ×6
                                              = 9.12 m3
Sr. No.
Material
Unit
Quantity
Rate
Amount
P.
1.
Cement
Bags
44
350/-
15400
00
2.
Sand
m3
4.56
1000/-
4560
00
3.
Aggregate
m3
9.12
1200/-
10944
00
                                                                                                       Total Amount = ₹ 30904.00/-

Sr. No.
Labour
Men (nos.)
Rate
Per(Day)
      Amount
P.
1.
Head Mason
½
400/-
Day
200
00
2.
Mason
350/-
Day
525
00
3.
Male Mazdoor
12
200/-
Day
2400
00
4.
Coolie
18
150/-
Day
2700
00
5.
Bhisti
3
250/-
Day
750
00
6.
T&P
Lump sum
100/-
__
100
00
                                                                                          Total Amount = ₹ 6675.00/-
Total cost = Cost of materials+ Cost of labours
                     30904.00+6675.00
Total cost = ₹ 37579.00/-

Add 1.5% Water Charges of total cost
                                              = (1.5/100 ) ×37579
        Water charges = ₹ 563.69/- (say = ₹ 564.00/-)

Add 10% Contractor’s Charges = (10/100 ) ×37579
           Contractor’s Charges = ₹ 3758.90/- (say = ₹ 3759.00/-)
                                                  ____________________________________________

         Grand total = 37579.00+564.00+3759.00
                                     = ₹ 41901.00/-