We Provide you knowledge about Civil Engineering's different subject or fields information with a easy & understandable language.
For more knowledge visit our YouTube channel have name LEARN CIVIL TECH & TRICKS.
Hope you like it.
Q. Prepare Rate analysis for a PCC work (1:3:6). Sol n .:- Given: - Concrete grade = M10 (1:3:6) Take = 10m 3 volume for PCC Add 52% extra for voids to get dry vol m . of Concrete. Volume of dry concrete = 1.52×10 = 15.2 m 3 Quantity of cement = (15.2/(1+3+6) ) ×1 ...
In this
method, the longer walls in a building are taken as long walls & calculated
from out-to-out & the partition
or shorter walls which make the right angle with the long walls are taken as
short walls and are calculated from in-to-in
for a particular layer of work. To calculate the quantities multiplying the
lengths of long & short walls by the breadth & the height of wall. These
lengths of long and short walls differ in each layer of footing.
PROCEDURE:-
1. Prepare the foundation plan
shown in fig. with all dimensions. Centre-to-Centre dimensions are taken out by
adding half width of each cross wall to inner dimension of room.
2. Now divide the walls into two
groups. In plan, walls in the horizontal direction are called Long walls &
vertical direction walls are called Short walls & Vice-Versa.
3. Measure the length of long
wall for an item by using formula-
Length
of Long wall for an item = length of long wall C/C + One width of an item (Half
width of each end)
4. Measure the length of short
wall for an item by using formula-
Length
of Short wall for an item = length of short wall C/C - One width of an item
(Half width of each end)
5. Multiply no., length, width,
& depth/height to get quantity of an item.
Q. Prepare Rate analysis for a PCC work (1:3:6). Sol n .:- Given: - Concrete grade = M10 (1:3:6) Take = 10m 3 volume for PCC Add 52% extra for voids to get dry vol m . of Concrete. Volume of dry concrete = 1.52×10 = 15.2 m 3 Quantity of cement = (15.2/(1+3+6) ) ×1 ...
Comments
Post a Comment