How to Prepare Rate Analysis for P.C.C. Work

Image
Q. Prepare Rate  analysis  for a PCC work (1:3:6). Sol n .:-              Given: -  Concrete grade = M10 (1:3:6)                                           Take = 10m 3  volume for PCC Add 52% extra for voids to get dry vol m . of Concrete. Volume of dry concrete = 1.52×10                                                    = 15.2 m 3 Quantity of cement = (15.2/(1+3+6)   ) ×1              ...

CENTRE LINE METHOD


In Centre line method, the length of Centre line is calculated & it is used for calculating the quantities of different items. In this method, the length will remain same for excavation in foundation, for concrete in foundation, for all footings & for superstructure. This method is simple & rapid, but it needs special attention & consideration at the junctions, meeting points of the cross or partition walls etc. This method is quite simple for rectangular, circular & polygonal buildings having no inner or cross walls.

PROCEDURE:-                                                                                                     
1. Prepare the foundation plan of given drawing write the Centre line length of each wall in.

2. Find the total length of Centre line of all walls.  

3. Calculate the number of junctions of cross walls each should be noted that corners of building where two walls meet are not taken in junction & if two walls meet at same point take n = 2 at the point.

4. For an item calculation of length is done as below-
Length of an item = total Centre line length – n × (½ × width of item)                                                                                                               where n = no. of junctions   

5. Multiply no., length, width, & depth/height to get quantity of an item.